Sectors
Power
Sub Sectors
Hydroelectric
Services
Design & Engineering
Location
Maharashtra, India
The Bhira Pumped Storage Hydropower Project is located in Raigad district of Maharashtra and forms part of an established hydropower system supporting the Mumbai Pune region. The original Bhira power station was commissioned in 1927 and comprises 6 generating units of 25 MW each, equipped with double overhang Pelton turbines. Along with other hydro and thermal stations in the region, the facility plays a key role in sustaining industrial and urban power demand.
To address the growing requirement for peaking power and grid stability, a pumped storage unit was developed as an extension to the existing hydropower station. The project was conceived to operate in both generation and pumping modes, enabling energy storage and rapid response to peak load conditions. At the time of its commissioning, the Bhira pumped storage unit was the single largest such unit in India and was perhaps the only pumped storage unit in the country capable of operating in both pumping and generation modes.
The scheme utilises the existing Mulshi lake as the upper reservoir, with a live storage capacity of 523.02 million m³, and an existing downstream pickup pond as the lower reservoir, with a live storage capacity of 1.536 million m³. The project involved rehabilitation of an existing low pressure headrace tunnel and construction of a new water conductor system, including large diameter penstocks, underground pressure shafts and a shaft type powerhouse.
Comprehensive hydraulic scale model studies of the entire water conductor system were carried out, along with detailed testing of rock properties in the tunnels. On site performance monitoring of the new penstock system was undertaken using vibrometers and strain gauges at critical locations. Following statutory clearances, site works commenced in February 1992, and the pumped storage unit was successfully commissioned in May 1997.
TCE’s scope
TCE provided end to end engineering and project management services for the Bhira Pumped Storage Hydropower Project, covering the full project lifecycle from concept to commissioning. The scope included preparation of the detailed project report and execution of site investigations, including geological and geotechnical studies.
TCE assisted in obtaining techno economic, forest and environmental clearances from state and central authorities and supported the project during international funding appraisal. The scope also covered preparation of technical specifications, bid documents and evaluation of bids.
Detailed engineering design and drawings were carried out for civil structures, water conductor systems, hydro mechanical works and electrical systems. This included engineering of the 4.53 km long concrete lined headrace tunnel of 4.267 m diameter, the orifice type surge shaft with diameters ranging from 17.5 m to 14.5 m and a depth of 62 m, underground and surface penstocks with diameters up to 3.7 m, a steel lined inclined pressure shaft, a shaft type powerhouse, and a concrete lined tailrace tunnel.
TCE also engineered the electrical systems, including the 220 kV switchyard and the 108 km long 220 kV transmission line. Vendor drawing review, inspection and expediting during manufacturing and erection, and construction supervision at site formed part of the scope. TCE supported commissioning and performance testing, including on site monitoring of penstock behaviour using strain gauges and vibrometers.
Impact
The Bhira Pumped Storage Hydropower Project represented a major advancement in pumped storage development in India. As the largest pumped storage unit in the country at the time of commissioning, and one of the very few capable of sustained operation in both pumping and generation modes, the project demonstrated the technical feasibility and operational value of large scale energy storage for grid support.
With an installed capacity of 150 MW operating at 500 rpm, supported by a 176.5 MVA synchronous generator rated at 11 kV and a 200 MVA transformer rated at 11/220 kV, the project strengthened peak load management and enhanced grid reliability. Integration of pumped storage capability with an existing hydropower station enabled more efficient utilisation of available water resources and improved operational flexibility.
The successful execution of deep underground works, large diameter steel lined penstocks, complex hydraulic systems and high capacity electrical infrastructure established important benchmarks in pumped storage engineering in India and contributed to the long term resilience of the regional power network.
About Us
Overview Our Leadership MilestonesSubsidiaries
- Ecofirst - Tata Consulting Engineers USA, LLC Corporate Social Responsibility Corporate GovernanceMedia
Media Kit Notices Annual Reports Marketing Collateral Videos TCExpressions Press Releases Press Coverage© Tata Consulting Engineers Limited. All Rights Reserved | Site Credits:DV





