Sectors
Power
Sub Sectors
Thermal
Services
Design & Engineering
Location
Saudi Arabia
The project involved a large scale thermal power plant with an installed capacity of 4 x 600 MW, executed in phases. Each unit consisted of a boiler and turbine generator system with a turbine rated at 625 MW operating at 3600 rpm.
Cooling water systems utilised sea water supplied through 4 pumps, each rated at 27900 cubic metres per hour. Fresh water requirements were met through desalination units producing 4000 cubic metres per day per unit. The plant incorporated advanced governing and protection systems to support on load testing and stable operation.
TCE’s Scope
TCE provided commissioning support services including trial operation assistance, performance guarantee testing and review and updating of commissioning documentation during plant takeover.
Impact
TCE played a key role during the commissioning and takeover phase of high capacity thermal generating units, supporting stable transition from construction to commercial operation for a large-scale utility power project.
About Us
Overview Our Leadership MilestonesSubsidiaries
- Ecofirst - Tata Consulting Engineers USA, LLC Corporate Social Responsibility Corporate GovernanceMedia
Media Kit Notices Annual Reports Marketing Collateral Videos TCExpressions Press Releases Press Coverage© Tata Consulting Engineers Limited. All Rights Reserved | Site Credits:DV